KATHMANDU, April 16: The Nepal Electricity Authority (NEA) has decided to cut the load-shedding time by two hours a day with effect from Friday, thanks to snow-melting in high Himalayas taking place in the recent days.
The 70 MW Middle Marsyangdi Hydro Project (Mid-Marsyangdi) has been generating electricity in its full capacity in the evening for two to three hours for past one week. One of the two turbines is producing around 20 to 35 MW of electricity round the clock. The Mid-Marsyangdi has two turbines each with generation capacity of 35 MW.
The 70 MW Middle Marsyangdi Hydro Project (Mid-Marsyangdi) has been generating electricity in its full capacity in the evening for two to three hours for past one week. One of the two turbines is producing around 20 to 35 MW of electricity round the clock. The Mid-Marsyangdi has two turbines each with generation capacity of 35 MW.